This is the project specifications section of a Tswelopele Local Municipality works tender. It sets out requirements for proving underground services before excavation, the relocation of existing services, and the appointment of a SANAS accredited geotechnical laboratory by the contractor. The Project Specification takes precedence over the standard specifications where they conflict.
Facts
Places
Free State
Key Takeaways
- Tswelopele Local Municipality
- Project Specification takes precedence over Standard and Particular Specifications
- Proving of services at least two weeks before programmed start
- Appointment of SANAS accredited geotechnical laboratory with minimum 3 quotations
- Tswelopele Local Municipality
- SANAS
- SANS 1921-1
- SANS 1921-2
Dates
Closing Date
Closing date not stated in the source