Witzenberg Municipality gives notice that its council, on 29 July 2026, accepted Eskom's quotation for an additional 5 MVA of electricity. Consumers allocated part of this capacity must pay R 5 693.62 per kVA, excluding VAT, on top of other charges. The resolution and supporting documents can be inspected at municipal offices and public libraries until 23 November 2026.

Facts

Places

Western Cape

Amounts

R 5 694

Parties

Witzenberg Municipality gives notice that its council

Key Takeaways

  • Council resolution of 29 July 2026 accepting Eskom quotation for additional 5 MVA
  • Contribution of R 5 693.62 per kVA, exclusive of VAT
  • Documents available for inspection until 23 November 2026
  • Signed by D. Nasson, Municipal Manager
  • Witzenberg Local Municipality
  • Eskom
  • D. Nasson