Quarterly reporting on energy loss reduction progress
The Ba-Phalaborwa Municipality must submit quarterly progress reports on efforts to reduce energy losses, starting from 30 September 2024.
The municipality was required to submit a progress report on the reduction of energy losses on a quarterly basis, commencing on 30 September 2024.
Places
Limpopo
Reference
NER/D/NP334
Application for 16.17% electricity tariff increase for 2025/26 financial year
Ba-Phalaborwa Municipality is seeking approval from the National Energy Regulator of South Africa to increase electricity tariffs by 16.17% for the 2025/26 financial year due to rising energy losses and declining profitability.
The municipality is applying for 16.17% in the 2025/26 financial year.
Meter replacement project for 500 single-phase split meters
The municipality plans to replace 500 single-phase split meters as part of its effort to reduce energy losses caused by outdated infrastructure and metering issues.
The municipality is planning to implement two projects for meter replacements with internal funding. The first project is to replace 500 single-phase split meters, and the second one is to replace the 107 LPU meter with digital meters.
Application for 16.17% tariff increase for the 2025/26 financial year
Ba-Phalaborwa Municipality is seeking approval from the National Energy Regulator of South Africa (NERSA) to increase electricity tariffs by 16.17% for the 2025/26 financial year, due to rising energy losses and declining profitability.
The municipality is applying for 16.17% in the 2025/26 financial year.
Meter replacement project for 107 LPU meters with digital meters
The municipality plans to replace 107 LPU meters with digital meters to improve meter accuracy and reduce energy losses.
The municipality is planning to implement two projects for meter replacements with internal funding. The first project is to replace 500 single-phase split meters, and the second one is to replace the 107 LPU meter with digital meters.