Construction of a gas distribution facility in Benoni South
The licence allows Sasol Gas to construct a natural gas distribution facility, including a pipeline extension and service pipeline, with specified technical parameters such as material composition, pressure limits, and flow capacity. The facility must be completed within 36 months of the licence issue date.
The facility contemplated in paragraph 1.1 above must be completed and become operational within 36 months of the date of issue of this licence.
Places
Ekurhuleni, Gauteng
Reference
https://www.nersa.org.za/file/8281/Annexure1_LicenceConditionsforSasolGasconstructionofDistributionFacilityintheBenoniarea.pdf