Submission of quarterly smart efficiency plan
The Thaba Chweu Local Municipality must submit a quarterly smart efficiency plan with identified measures to reduce energy losses by 30 September 2026.
The document's recorded date is 1 July 2026. Confirm on the official source.
2.3 require the municipality to submit a quarterly smart efficiency plan, with improvement measures identified to reduce losses, by 30 September 2026;
Reference
https://www.nersa.org.za/file/9339/ThabaChweuRFD26-27.pdf
Parties
The municipality, Eskom debt to NERSA. The decisions were made following a review and consideration of the municipality
Closing Date
1 July 2026
Submission of COS study cost report for audit
The Thaba Chweu Local Municipality must submit a detailed report on all costs included in its Cost of Supply study to the National Energy Regulator of South Africa (NERSA) for independent verification or audit.
The document's recorded date is 1 July 2026. Confirm on the official source.
2.2 that the municipality submit a report accounting for all costs noted in its COS study, to enable the National Energy Regulator of South Africa (NERSA) to perform its independent verification/audit process by 31 January 2027;
Implementation of approved tariffs for 2026/27 financial year
The Thaba Chweu Local Municipality is approved to implement new electricity tariffs based on the Cost of Supply study, effective from 1 July 2026. These tariffs will apply to all electricity users within the municipality.
The document's recorded date is 1 July 2026. Confirm on the official source.
2.1 to approve the tariffs based on the Cost of Supply (COS) study, as recommended in the tariff analysis section, for implementation by the municipality with effect from 1 July 2026;
Submission of Eskom debt report
The Thaba Chweu Local Municipality must submit a formal report on its outstanding debt to Eskom.
The document's recorded date is 1 July 2026. Confirm on the official source.
2.4 require the municipality to submit a report on its Eskom debt.