Submission of quarterly smart efficiency plan
The Mogalakwena Local Municipality must develop and submit a quarterly plan outlining measures to reduce high energy losses in its network.
The document's recorded date is 11 May 2026. Confirm on the official source.
that the municipality must submit a quarterly smart efficiency plan with improvement measures identified in reducing high energy losses and submit by 30 September 2026
Reference
https://www.nersa.org.za/file/9264/MogalakwenaMunicipality_ReasonsforDecisionontariffapplicationprocessforFY2026-27FY.pdf
Parties
The approval is based on the municipality, Cost of Supply Study and includes requirements
Closing Date
11 May 2026
Submission of COS cost report for audit
The Mogalakwena Local Municipality must submit a detailed report on all costs included in its Cost of Supply Study to allow the National Energy Regulator of South Africa to conduct an independent verification or audit.
The document's recorded date is 11 May 2026. Confirm on the official source.
that the municipality must submit a report accounting for all the costs that have been noted in its COS study to enable the National Energy Regulator of South Africa to perform its independent verification/audit process by 31 January 2027
Implementation of approved tariffs for 2026/27 financial year
The Mogalakwena Local Municipality is authorised to implement new electricity tariffs based on the Cost of Supply Study, effective from 1 July 2026. These tariffs will apply to all electricity consumers within the municipality.
The document's recorded date is 11 May 2026. Confirm on the official source.
approve the tariffs that are based on the Cost of Supply (COS) Study as recommended in the tariff analysis section for implementation by the municipality with effect from 1 July 2026