ARBITRATION TO PROCEED
The parties must continue arbitration under the pre-arbitration agreement, exchange information, and work towards a final, binding and sustainable resolution.
The document's recorded date is 17 June 2026. Confirm on the official source.
The arbitration (under the pre- arbitration agreement) must continue without delay.
Places
Eastern Cape
Reference
https://bnlm.gov.za/documents?upf=dl&id=6481
Parties
Eskom may not interrupt electricity supply to the municipality
Closing Date
17 June 2026
CONTINUITY OF ELECTRICITY SUPPLY
Dr Beyers Naudé Local Municipality is entitled to continued electricity supply while the disputes are resolved, and Eskom may not interrupt that supply.
The document's recorded date is 17 June 2026. Confirm on the official source.
Eskom must continue supplying electricity and may not interrupt supply to the Municipality.