Mec Motsumi Updates On Progress Made In The Construction Of The New Shaleng And Mothelesi Replacement Schools In Taung
Official source
Source domain: idt.org.za
Collected on 29 July 2026
Always confirm details on the official source before acting.
What this means
What this document offers
Read out of this document by Govermate's AI, in its own words. Each one quotes the line it came from — confirm on the official source before acting.
Construction tender documentation preparation (for the replacement schools projects)
The project programme anticipates that after the Detailed Design review, construction tender documentation will be prepared for the replacement schools for Shaleng Secondary and Mothelesi Primary.
- Who it is for
- potential construction contractors/tenderers (implied by the tender documentation and tender advertisement milestones)
- How to act on it
- No application or submission process is described; the statement only sets out expected programme milestones for tender documentation and advertisement.
Show the line this came from
The Detailed Design Stage is expected to take approximately five months to complete and will culminate in the preparation of construction tender documentation.
Advertisement of construction tender (replacement schools projects)
The project programme anticipates advertisement of the construction tender for the replacement schools.
- Who it is for
- potential construction contractors/tenderers (implied by the tender advertisement milestone)
- How to act on it
- No tender access instructions are provided in the supplied text.
Show the line this came from
• Advertisement of C
Facts
Places
North West
Reference
DOCUMENTATION FINALISATION NOVEMBER 2026
Key Takeaways
- Date of statement: 12 June 2026
- Location: Shaleng Village near Taung (North West)
- Projects: replacement schools for Shaleng Secondary and Mothelesi Primary
- Security fence erected by Cochrane Construction starting September 2024
- ClearVu security fence completed: 9 December 2024
- Implementing agent: Independent Development Trust (IDT)
- Dolomite assessment reviewed/approved by the Council for Geoscience
- Feasibility approved and Site Development Plan approved
- Concept Design completed; under Department review
- Detailed Design expected duration: ~5 months
- Milestones: Detailed Design completion October 2026; tender documentation finalisation November 2026; tender advertisement January 2027; contractor appointment March 2027
- Viola Motsumi
- North West Department of Education
- Independent Development Trust (IDT)
- Cochrane Construction
- Council for Geoscience
- Vuyo Mantshule
- Dr Elias Malindi
Dates
Closing Date
9 December 2024