Gauteng Roads and Transport introduces measures to ease weekend traffic congestion at Olifantsvlei Cemetery
Official source
Source domain: gov.za
Collected on 27 July 2026
Always confirm details on the official source before acting.
What this means
What this document offers
Read out of this document by Govermate's AI, in its own words. Each one quotes the line it came from — confirm on the official source before acting.
Weekend traffic congestion easing measures for travellers to Olifantsvlei cemetery
GDRT says it has agreed on short- and long-term measures with the City of Johannesburg and project contractors to improve traffic flow and safety for motorists and mourners travelling to Olifantsvlei cemetery, especially on weekends, while rehabilitation work is underway on the R553.
- Who it is for
- Motorists and mourners travelling towards Olifantsvlei cemetery, particularly during weekends
- How to act on it
- Use the road network around Olifantsvlei cemetery and follow temporary signage and instructions; motorists will receive regular updates on construction activities, anticipated delays and alternative routes.
Show the line this came from
The Gauteng Department of Roads and Transport (GDRT), in collaboration with the City of Johannesburg, and the project contractors have agreed on a series of short and long-term measures to address traffic congestion experienced by motorists and mourners travelling towards Olifantsvlei cemetery, particularly during weekends.
Facts
Places
City of Johannesburg, Gauteng
Reference
R554/STOCKWELL
Amounts
R 553, R 554, R 558
Key Takeaways
- Issuing organisation: Gauteng Department of Roads and Transport (GDRT)
- Collaboration: City of Johannesburg and project contractors
- Location: Olifantsvlei Cemetery; traffic routes include R553 (Golden Highway) and R554, Fun Valley, Stockwell and Golden Highway intersections
- Stakeholder engagement meeting date: Thursday, 16 July 2026
- Ongoing works: heavy rehabilitation along R553 from R558 intersection to just beyond M68 (Chris Hani Road/Columbine Avenue)
- Expected project completion: mid-September 2026
- Short-term measures: suspend all construction activities over weekends
- Short-term measures: asphalt surfacing at Stockwell intersection on 17 July 2026 and 20 July 2026
- Short-term measures: kerbing and pedestrian walkway paving at Stockwell intersection by end of July 2026
- Short-term measures: deploy traffic accommodation teams supported by law-enforcement officers at key intersections during high-traffic periods
- Short-term measures: install additional temporary barriers to discourage illegal turns
- Short-term measures: prioritise grass-cutting adjacent to the cemetery to improve visibility
- Communication: regular updates to motorists on construction activities and anticipated delays/alternative routes
- Permanent improvements: completion of permanent road markings and commissioning of new traffic signals at R554/Stockwell intersections
- MEC appeal for caution: Kedibone Diale-Tlabela urges road users to obey temporary signage and instructions
- Media enquiries: Ms Melitah Madiba (Head of Communications) and Mr Lesiba Mpya (MEC’s Spokesperson)
- Gauteng Department of Roads and Transport (GDRT)
- City of Johannesburg
- Olifantsvlei Cemetery
- Gauteng MEC for Roads and Transport: Kedibone Diale-Tlabela
- Ms Melitah Madiba
- Mr Lesiba Mpya
- R553 (Golden Highway)
- R558 intersection
- M68 (Chris Hani Road/Columbine Avenue)
- R554
- Stockwell intersection
- Fun Valley
- Chris Hani Road
- Columbine Avenue
Dates
Opening Date
24 July 2026
Closing Date
16 July 2026