Lingcom Primary School Upgrade Project Enhances Learning Environment and Community Development

Eastern Cape Department of Public Works and InfrastructureRef: https://www.ecdpw.gov.za/lingcom-primary-school-upgrade-project-enhances-learning-environment-and-community-development/

Official source

Source domain: ecdpw.gov.za

Collected on 13 July 2026

Always confirm details on the official source before acting.

What this means

This is a news/media statement from the Eastern Cape Department of Public Works and Infrastructure (DPWI) about the delivery of the Lingcom Primary School Upgrade Project. The project involved repairs, renovations and additions, initially awarded at R77,981,559.32 and revised to about R87,903,226.30, with construction starting on 07 December 2017 and completing on 08 December 2025 (the school was occupied since May 2025). The upgrade delivered new classrooms and facilities (including Grade R, administration, nutrition centre, ablution blocks, library/computer centre, science laboratory, and security works) and included external works and an approximately R7.5 million subcontracting allocation with a 30% SMME participation target.

Facts

Places

Eastern Cape

Reference

https://www.ecdpw.gov.za/lingcom-primary-school-upgrade-project-enhances-learning-environment-and-community-development/

Amounts

R 77 981 559, R 87 903 226, R 7 500 000

Key Takeaways

  • Project: Lingcom Primary School Upgrade Project (repairs, renovations and additions)
  • Implementing agent role: Eastern Cape DPWI for the Department of Education
  • Contract value initially: R77,981,559.32
  • Contract value revised to: ~R87,903,226.30
  • Construction commenced: 07 December 2017
  • Original contract period: 24 months; planned completion: January 2020
  • Actual completion: 08 December 2025
  • School occupied since: May 2025
  • Delivered: 17 new classrooms in eight classroom blocks
  • Delivered: Grade R facility with dedicated kitchen
  • Delivered: administration building; fully equipped nutrition centre
  • Delivered: two ablution blocks; library and computer centre; science laboratory
  • Security works: fencing and guardhouse
  • External works: roads, parking, assembly areas, ramps, paving
  • Inclusive economic development: ~R7.5 million subcontracting
  • SMME participation target: 30%
  • Post published date: 9 July 2026
  • Eastern Cape Department of Public Works and Infrastructure (DPWI)
  • Department of Education
  • Lingcom Primary School
  • Project Manager (construction team)