First phase of wind energy feed-in from Ummbila Emoyeni One Wind Energy Facility
The first 155MW of wind energy from Seriti Green’s Ummbila Emoyeni One Wind Energy Facility can now be fed into the national grid, starting from 28 November 2025, due to the successful commissioning of the Vunumoya MTS.
The document's recorded date is 26 November 2025. Confirm on the official source.
Places
Mpumalanga
Reference
https://www.eskom.co.za/seriti-green-and-eskom-mark-handover-of-vunumoya-main-transmission-station/
Amounts
R 1 000 000 000
Closing Date
26 November 2025
It also enables the first 155MW of wind energy from Seriti Green’s Ummbila Emoyeni One Wind Energy Facility to be fed into the system ahead of schedule, marking the beginning of a 900MW programme that will progressively add further renewable capacity.
Vunumoya Main Transmission Station (MTS) handover and integration into the national grid
The Vunumoya Main Transmission Station has been formally handed over from Seriti Green to Eskom. It is now fully energised, operational, and integrated into the national electricity grid, enabling the flow of renewable energy from the Ummbila Emoyeni One Wind Energy Facility.
Seriti Green, together with Eskom and its subsidiary, the National Transmission Company South Africa (NTCSA), are proud to announce the formal handover of the Vunumoya Main Transmission Station (MTS) by Seriti Green to Eskom.